Cavell Bridge 90ft x 27.6ft (Scenic Rim Regional County)

image1-1
IMG_0594
IMG_0598
IMG_0602
IMG_0600
IMG_0155-rotated
IMG_0596
IMG_0593
IMG_0597-scaled
IMG_0157-rotated
IMG_0133
Click to download the Full Case Study

Cavell Bridge is the second of two InQuik bridges constructed by Scenic Rim Regional Council using their own in-house construction crew.

The bridge replacement project was jointly funded by Council and the Australian Governmentunder the Bridges Renewal Programme Round Three.

Council entered into the Bridges Renewal Programme Round Three funding agreement with the Australian Government, for up to $557,150 (GST exclusive) for the Cavell Bridge replacement project, with Council’s contribution of $557,150 (GST exclusive) to be funded from Council’s Capital Bridge Replacement Program;

InQuik were engaged by County to provide detailed design for the complete project including the detailed civil design of the road approaches and the piling design. SMEC – PDR was the design partner for this project.

County work crews completed the construction of the project. County subcontracted the
demolition of the existing timber bridge. County work crews then constructed an earthworks pad at the central pier to the underside of the headstock to allow for piling and the installation of the pre-fabricated headstock. Piling works were completed by Councils subcontractor.

County crews then installed both Magnelis-clad abutments which were 27.6ft in length,
4ft high to the underside of the deck and 3ft-wide with a 2.3ft stepped backwall and approach slab pocket; as well as the headstock. The SM1600-rated deck panels were installed simply supported over the abutments and headstocks using elastomeric bearing strips.

Each abutment came preassembled with 2 x wing walls, which are 6.2ft-high and 5.9ft-long and angled at 45 degrees to the abutment.

The abutments were backfilled and the approach concrete slabs constructed followed by the remaining approach road works and guardrail.

Key Project Points

  • Initially the design was a single span 59ft x 27.6ft and was amended to 90ft x 27.6ft multi-span set with a 4% crossfall. The revised length and crossfall was introduced to facilitate a re-alignment of the bridge improving the horizontal geometry of Boyland Road. This design is a unique bridge for the InQuik System, however as the design changed InQuik were able to adapt and supply modular components to suit.
  • Council work crews completed the construction of the project. Council subcontracted the demolition of the existing timber bridge and the piling works.

Challenges

  • The project faced a number of challenges identifying the interfaces of design ownership between the civil design, the standard InQuik bridge elements and the overall structural design to cover flood loading, bridge joints and piling connections.
  • The detailed site specific design identified that the standard InQuik bridge elements were inadequate to resist flood loading. Although the structural elements were adequate, the proposed upstands on the edges of the headstocks did not provide adequate resistance to the lateral loading from flooding. Furthermore, buoyancy checks identified that the bridge would be subject to uplift. The standard InQuik tie-downs were adequate to resist the uplift, however were not adequate to resist the lateral loading. This was resolved with the design of lateral restraint blocks.
Location:
Bourke Road
Client:
Southern Downs Regional Council
Span and Width:
90ft x 27.6ft
Start Date:
End Date: